Request for Raw Materials from Sales Order

هذا المحتوى غير متوفر بلغتك بعد.

Create a Material Request directly from one submitted Sales Order when you need to procure raw materials for its manufactured Items. Use a Production Plan when planning several Sales Orders or broader production demand together.

Confirm:

  • The Sales Order is submitted.
  • Each manufactured Item has an active default Bill of Materials.
  • BOM quantities and UOMs are correct.
  • Warehouses and projected quantities are current.
  • You have permission to create and submit Material Requests.

This action is intended for manufactured Items. A purchased finished good without a BOM will not produce raw-material requirements.

  1. Open the submitted Sales Order.
  2. Select Create.
  3. Select Request for Raw Materials.

The Sales Order Create menu with Request for Raw Materials highlighted.

Bravo Hub ERP opens a dialog containing eligible finished Items with BOMs.

  1. Review the finished Items and required quantities.
  2. Change the BOM only when another valid BOM should be used.
  3. Select the source and target Warehouses or other options shown by your version.
  4. Choose whether to include exploded Items or ignore existing ordered quantity.
  5. Select Create or Make.

Bravo Hub ERP creates a Material Request containing the calculated raw materials.

Check:

  • Material Request Type.
  • Schedule Date.
  • Item, Quantity, UOM, and Warehouse.
  • Links to the Sales Order and BOM.
  • Projected stock and existing supply.

The generated Material Request with calculated raw-material rows.

The dot before an Item Code shows stock availability at a glance: green means in stock and red means out of stock. Select the highlighted pencil icon to open the full child-row editor when you need additional planning fields.

Submit the Material Request only after confirming that it will not duplicate existing procurement or production supply.

OptionEffect
Include Exploded ItemsUses lower-level raw materials from multi-level BOMs instead of only the immediate components
Ignore Existing Ordered QtyRequests the calculated requirement without reducing it for quantities already ordered
BOMSelects which active BOM supplies the component structure

Field labels can vary by version. Review the generated Items rather than relying only on the option name.

RequirementRecommended workflow
One Sales Order needs raw-material procurementRequest for Raw Materials from Sales Order
Several Sales Orders need consolidated planningProduction Plan
Manufacture and operations must be scheduledProduction Plan and Work Orders
Replenishment is driven by stock levelsReorder or Material Request planning
ProblemWhat to check
Menu action is missingConfirm the Sales Order is submitted and contains a manufactured Item with a valid BOM
Finished Item is absent from the dialogCheck the default and active BOM
Quantities are unexpectedReview Sales Order Qty, BOM Qty, conversion factors, scrap, and exploded-item behavior
Duplicate procurement is suggestedReview projected quantity and avoid Ignore Existing Ordered Qty unless intentional
Wrong Warehouse is usedReview Item, BOM, Company, and dialog Warehouse defaults

No. It creates a Material Request. Continue through your procurement workflow to create a Request for Quotation or Purchase Order.

Is the Material Request submitted automatically?

Section titled “Is the Material Request submitted automatically?”

Confirm the resulting document’s status in your current version and approval workflow. Review it before submission.

Yes, when the dialog permits selecting another active BOM.

Should I enable Ignore Existing Ordered Qty?

Section titled “Should I enable Ignore Existing Ordered Qty?”

Only when you intentionally want to request the full requirement despite existing supply.