Asphalt Plant — Production & Quality

A batch pulls its raw-material recipe from an Approved Mix Design and lets the operator record the actual quantities used, so target vs. actual variance is derived automatically per material.

On submit, a batch:

  1. Checks the mix temperature is within the plant’s configured window (default 140–165 °C) — outside that range, submission is rejected.
  2. Checks each actual material quantity doesn’t exceed what’s on hand in its silo.
  3. Posts a Stock Entry (Manufacture) that consumes the raw materials from their silos and produces the finished asphalt into the finished-goods warehouse.
  4. Re-prices the batch’s material cost from what the Stock Entry actually posted (FIFO/Moving Average), not the estimate used at validation time — the estimate can be stale by the time the batch is produced.

Cancelling a batch reverses its Stock Entry. Cancellation is blocked while a submitted Quality Test still exists against the batch — the test has to be cancelled first.

If a batch fails quality, the plant marks it Rejected. Rejecting a batch posts a second Stock Entry that moves its tonnage into a dedicated reject warehouse, so it drops out of the finished-goods stock available for dispatch. Asphalt can’t be held back pending lab results the way a discrete part can — it’s usually already loaded or in the silo by the time results come back — so rejection is a status + stock-move control rather than a physical batch/lot hold. A Delivery Ticket checks the batch’s status at ticket time and is rejected if that batch has since been marked Rejected.

Records per-parameter pass/fail results against a batch (temperature, gradation, asphalt content, etc.), with an overall pass/fail derived from the parameter rows. A submitted quality test blocks its batch from being cancelled until the test itself is cancelled.